Stalled public works in Peru: the World Bank estimates half of projects are halted

About half of the 120,000 to 140,000 active public investment projects in Peru are halted, stalled or abandoned, according to the World Bank at CADE 2026. Finishing the backlog would cost S/ 654 billion. The Comptroller's Office counts 2,237 stalled works. Figures by region.

· By , journalist

Stalled public works in Peru: the World Bank estimates half of projects are halted

Photo: El Surquillano, CC0, Wikimedia Commons

About 50% of the active public investment projects in Peru, between 120,000 and 140,000 in early 2026, are halted, stalled or abandoned, according to a presentation by World Bank economist Antonio Cusato at CADE Ejecutivos 2026, reported by Gestión on November 25. The outstanding balance to finish those projects totals S/ 654 billion, 60% of GDP: more than ten years of public investment devoted solely to completing what has already been started.

At the same event, in Urubamba (Cusco), Central Reserve Bank president Julio Velarde said that "public management is not bad, it is terrible," according to La República. These are the World Bank and Comptroller's Office figures on stalled public works in Peru, by region, by level of government and by size.

Stuck public investment in Peru
~50%Projects haltedof 120,000-140,000 active
S/ 654 bnOutstanding balance60% of GDP
2,237Stalled worksComptroller, November 2026
1,508In El Niño critical zones67.4% of the total
Source: World Bank via Gestión; Comptroller General's Office via Gestión.
View the data as a table
Projects halted~50%
Outstanding balanceS/ 654 bn
Stalled works2,237
In El Niño critical zones1,508

What the World Bank said about stalled public works in Peru

Cusato described a "structural crisis characterized by an overload of projects" and warned that "the traditional indicator for measuring project progress does not work": an entity can show it spent 92% of its annual budget even though its works remain unfinished. These are the figures he presented, according to Gestión:

IndicatorFigure
Active public investment projects (early 2026)120,000 to 140,000
Projects halted, stalled or abandonedAbout 50%
Outstanding balance to executeS/ 654 billion (60% of GDP)
Four-year execution, 2008-201180%
Four-year execution, after easing the SNIP from 201165%
New projects over S/ 1 million per yearFrom about 2,000 to over 4,000 since 2012
Projects added through budget amendments9 out of 10
Transport sector execution56%

Source: World Bank presentation at CADE Ejecutivos 2026, according to Gestión. The report does not link to a document published by the institution. According to the same presentation, projects added "at the last minute" have four-year execution rates up to 25 points lower than those planned 1.5 to 2 years in advance. The example cited was the Antonio Lorena hospital in Cusco: it started in 2011, was 20% complete after four years and took 13 years to be delivered.

New Antonio Lorena hospital building in Cusco, Peru
The Antonio Lorena hospital took 13 years to be delivered. Photo: Chalisimo5, CC BY-SA 4.0, Wikimedia Commons.

Stalled public works in Peru by region: Cusco has the most, Lima holds the money

The latest Comptroller's report with a breakdown by department, as of March 31, 2026, counted 2,241 stalled works with an investment cost of S/ 73.166 billion and S/ 35.196 billion still to execute (the report's text says S/ 32.196 billion, but its table adds up to 35.196). Cusco is the department with the most stalled works (338), followed by Puno (221) and Áncash (188); Lima has fewer works (164) but holds 32% of the money.

Cusco, the department with the most stalled worksStalled public works by department, March 31, 2026
Source: Comptroller General's Office, Report No. 001-2026-CG/SESNC, table 3.
View the data as a table
Cusco338
Puno221
Áncash188
Lima164
Cajamarca140
Ayacucho140
Arequipa126
Piura123
Apurímac87
Huancavelica85
La Libertad83
Junín81
Huánuco76
Lambayeque72
Amazonas44
Many small works in the highlands, few and costly ones in LimaStalled works and investment cost by department
05,00010,00015,00020,00025,0000100200300400Stalled worksS/ millionLimaLa LibertadPunoCusco
Source: Comptroller General's Office, table 3, as of Mar 31, 2026.
View the data as a table
Stalled worksS/ million
Lima16423,514
La Libertad838,518
Arequipa1268,383
Piura1233,848
Áncash1883,756
Cajamarca1403,344
Puno2213,084
Cusco3382,502
Huánuco762,352
Lambayeque721,838
Ica311,316
Tacna401,233
Apurímac871,108
Amazonas441,102
Ucayali271,096
Moquegua401,072
Tumbes12987
Junín81961
Loreto39776
Huancavelica85580
Ayacucho140569
San Martín16399
Pasco28355
Madre de Dios34326
Callao6148
Stalled works by department
Lima16423,514.18,747.5
La Libertad838,517.54,925.9
Arequipa1268,383.15,605.8
Piura1233,848.01,734.5
Áncash1883,756.11,344.2
Cajamarca1403,343.91,850.2
Puno2213,083.52,028.0
Cusco3382,502.3935.5
Huánuco762,351.72,000.2
Lambayeque721,838.4550.9
Ica311,316.4698.7
Tacna401,233.2687.2
Apurímac871,108.0504.0
Amazonas441,101.6452.7
Ucayali271,095.8293.8
Moquegua401,071.6365.5
Tumbes12987.4460.1
Junín81961.4508.8
Loreto39776.1325.3
Huancavelica85579.8269.0
Ayacucho140569.2264.7
San Martín16398.6197.1
Pasco28354.8143.5
Madre de Dios34325.7190.5
Callao6147.8113.0
Source: Comptroller General's Office, Report No. 001-2026-CG/SESNC (Mar 31, 2026).

Municipalities with the most works, the national government with the most money

Level of governmentStalled worksInvestment costBalance to execute
Local governments1,533 (68.4%)S/ 12.092 billionS/ 6.768 billion
National government391 (17.4%)S/ 42.564 billionS/ 17.045 billion
Regional governments317 (14.1%)S/ 18.510 billionS/ 11.384 billion
Total2,241S/ 73.166 billionS/ 35.196 billion

Source: Comptroller's report, table 4. Municipalities account for two out of three stalled works, but they are small projects: 716 of the 2,241 works cost up to S/ 1 million. At the other end, just 7 megaprojects worth more than S/ 1 billion add up to 43.8% of the total cost. Transport and communications is the sector with the most stalled works (626), according to the same report.

7 megaprojects hold 43.8% of the moneyInvestment cost of stalled works by size, S/ million
View the data as a table
Up to S/ 1 million327 · 716 works
S/ 1-3 million802 · 428 works
S/ 3-10 million3,382 · 589 works
S/ 10-100 million11,596 · 413 works
S/ 100-200 million4,394 · 35 works
S/ 200-1,000 million20,618 · 53 works
Over S/ 1,000 million32,048 · 7 works
Excavator and truck at a construction site in Lima
Transport is the sector with the most stalled works. Photo: El Surquillano, CC0, Wikimedia Commons.

How the number of stalled works changed in 2026 and the El Niño risk

  • March: 2,241 stalled works worth S/ 73.166 billion (Comptroller's report).
  • June: 2,262 works worth about S/ 62.828 billion, according to the report released by the Comptroller's Office in August (Infobae).
  • November: 2,237 works; 1,508 (67.4%) are in critical El Niño areas and finishing them would cost S/ 14.476 billion. Cusco (272), Puno (212), Ayacucho (149) and Áncash (118) account for most of them, according to what the Comptroller's Office told Congress (Gestión).
  • Restarted: through preventive oversight, the Comptroller's Office pushed for the restart of 109 works worth S/ 4.3 billion, according to the same presentation.
Stalled works in El Niño critical areasNumber
Total in critical areas1,508 (67.4% of 2,237)
Cusco272
Puno212
Ayacucho149
Áncash118
Transport and communications sector436
Housing, construction and sanitation sector319
Agriculture sector195
Education and culture sector195

Source: Comptroller's presentation to Congress's State Management Modernization Committee, according to Gestión (November 11, 2026). The four sectors in the table account for 75.9% of the stalled works in risk areas. With so many road, water and canal works left half-done, El Niño is a key concern: an unfinished work offers no protection.

The Comptroller's figures (works with a file and contract that have stalled) and the World Bank's (all halted investment projects) measure different things, which is why they differ so much. The issue comes amid the debate over Peru's 2027 budget and Velarde's warning that El Niño could shave up to 2% off GDP. For the pulse of the economy, see September growth according to INEI.

Frequently asked questions

How many stalled public works are there in Peru?

The Comptroller's Office reported 2,237 stalled works in November 2026. Its latest detailed report, as of March 31, counted 2,241 worth S/ 73.166 billion.

Which region has the most stalled works?

Cusco, with 338 as of March 31, 2026, followed by Puno (221) and Áncash (188).

What did the World Bank say?

That about half of the 120,000 to 140,000 active investment projects are halted, stalled or abandoned, and that finishing them would cost S/ 654 billion, 60% of GDP.

What did Julio Velarde say at CADE 2026?

That "public management is not bad, it is terrible" and that the state does not properly serve education and health despite the resources the economy generates.