The Santiago Metropolitan Region's Environmental Assessment Commission unanimously approved on November 19 Section 3 of Santiago Metro Line 9, which will extend the line about 8.31 km from La Pintana to Plaza de Puente Alto station, with five stations and a declared investment of US$786.9 million, according to the Section 3 file in the SEIA. The remaining step is the environmental rating resolution, which Metro expects in early December, Meganoticias reported.
With this section, the full Line 9 has 27 km and 19 stations between Recoleta and Puente Alto, and will bring the Metro for the first time to areas such as La Legua, La Pintana and Bajos de Mena. The trip from Puente Alto to downtown will take about 35 minutes, 28% less than today, according to Metro de Santiago.
View the data as a table
| Length | 27 km |
| Stations | 19 |
| People served | 2 million |
| Investment declared to the SEIA | US$ 2,733 M |
What the final Line 9 section to Puente Alto includes
According to the environmental impact study, Section 3 runs in a tunnel along Santa Rosa avenue in La Pintana, turns east along Sargento Menadier avenue in Puente Alto and heads north on Balmaceda avenue to connect with Line 4 at Plaza de Puente Alto. It includes five stations, six construction shafts that will later become ventilation shafts and a turnback track; stations are about 2 km apart on average.
| Item | Sections 1 and 2 | Section 3 |
|---|---|---|
| Route | Puente Cal y Canto - Plaza de La Pintana | La Pintana - Plaza de Puente Alto |
| Length | 18.6 km | 8.31 km |
| Stations | 14 + 1 for possible future use | 5 |
| Declared investment | US$1,946.1 million | US$786.9 million |
| People served | 1,300,000 | 700,000 |
| Filed with the SEIA | November 8, 2023 | June 9, 2025 |
| Environmental approval | Rating resolution of May 15, 2025 | Assessment commission, November 19, 2026 |
Sources: Line 9 file in the SEIA and Section 3 file in the SEIA. The investments are the amounts Metro declared to the Environmental Assessment Service and may change when the works are tendered. The table adds up to 26.9 km, which Metro rounds to 27 km.

When Metro Line 9 opens
- Nov 8, 2023Line 9 environmental impact study filedSections 1 and 2, from Recoleta to La Pintana.
- May 15, 2025Environmental approval of sections 1 and 2
- Jun 9, 2025Section 3 study filedLa Pintana - Plaza de Puente Alto.
- Nov 19, 2026Assessment commission approves Section 3Unanimously. Metro expects the resolution in early December.
- 2030Section 1 opens10 stations and 14 km between Bío Bío and Plaza de La Pintana.
- 2032Section 2 opensFrom Santa Rosa and Ñuble to downtown, including Santa Lucía and Puente Cal y Canto.
- 2033Section 3 opensTo Plaza de Puente Alto.
Sources: SEIA and Meganoticias. Opening dates are those announced by the government when the section was approved; the project was 5% complete overall. "These are state projects that go beyond any one government," said Louis de Grange, minister of both Public Works and Transport.
Which districts Line 9 connects and its transfers
Source: Metro de Santiago and SEIA. The line links eight districts: Recoleta, Santiago, San Miguel, San Joaquín, La Granja, San Ramón, La Pintana and Puente Alto; its northern turnback track lies in Independencia. It will have six transfer stations. Puente Cal y Canto will be the network's first four-line interchange, with lines 2, 3 and 7, and at Plaza de Puente Alto it will connect with Line 4, which Metro expects to relieve with a direct route downtown. To see what a ride costs today, check the 2026 Metro fare.
Metro Line 9 opening stages
| Stage | Route | Details | Opening |
|---|---|---|---|
| Section 1 | Bío Bío - Plaza de La Pintana | 10 stations, 14 km | 2030 |
| Section 2 | Santa Rosa and Ñuble - downtown Santiago | Includes Santa Lucía and Puente Cal y Canto | 2032 |
| Section 3 | La Pintana - Plaza de Puente Alto | 5 stations, 8.31 km | 2033 |
Sources: Meganoticias and SEIA. Section 1 ends at Gabriela station, on the Plaza de La Pintana; from there a tunnel leads to the line's depot and workshops, next to La Pintana's bus terminal, where Line 9 trains and those of future lines will be stored and maintained. Section 3 reuses that tunnel and adds a new station before continuing to Puente Alto.
Metro's stated goals for Line 9
- Bring La Pintana into the Metro network.
- Improve connections between downtown Santiago and the south.
- Ease congestion along Santa Rosa avenue, with less surface public transport.
- Improve service on lines 1, 2, 3, 5, 6 and 4A by spreading passengers out.
Source: Line 9 file in the SEIA. The Section 3 study adds about 700,000 people served in La Pintana and Puente Alto, bringing the line's total to 2 million, the same figure Metro reports.
Why Line 9 matters for La Pintana and Bajos de Mena
- La Pintana joins the Metro network for the first time, one of the project's stated goals.
- Bajos de Mena, in Puente Alto, gets a link to downtown that bypasses Line 4.
- Fewer surface buses on Santa Rosa: the line's study aims to ease congestion on that corridor.
- A 35-minute trip from Puente Alto to downtown, compared with about 50 minutes today.

Frequently asked questions
When will Metro Line 9 be ready?
In stages: section 1 in 2030, section 2 in 2032 and section 3, to Puente Alto, in 2033.
How many stations will Line 9 have?
19 stations over 27 km, according to Metro.
How much does the final section cost?
Metro declared an investment of US$786.9 million to the SEIA.
Where does Line 9 run?
Through Recoleta, Santiago, San Miguel, San Joaquín, La Granja, San Ramón, La Pintana and Puente Alto, mostly under Santa Rosa avenue.