Sociedad Concesionaria Nueva Aconcagua, part of VíasChile, filed on Monday, November 23, with Chile's Environmental Impact Assessment System (SEIA) the project to widen Route 5 North between Santiago and the El Melón tunnel, with an investment of US$456.2 million. It is an environmental impact study (EIA) and, according to the project file in the SEIA, it is "in admission." The section runs from kilometer 10.86, in Quilicura, to kilometer 127.1, at the tunnel's southern access in Nogales.
It is the first major piece of the second concession of Route 5 between Santiago and Los Vilos, which VíasChile has operated since February 2025. It includes fourth and third lanes, new service roads, interchanges, bridges and the replacement of toll booths with free-flow electronic tolling. This is what the project says, how much tolls cost today and when works would begin.
View the data as a table
| Investment | US$ 456.2 M |
| Kilometers of works | 116 |
| Third lanes | 102 km |
| Commissioning | 2,033 |
What works the Route 5 North project includes
The goal, according to the EIA, is to "improve the technical standard and service levels of Route 5" and modernize the concession's operation with "technological management and electronic toll collection systems." The detail of the works, according to Diario Financiero and the MOP concession page:
| Work | Where | Detail |
|---|---|---|
| Fourth lanes | Buenaventura to Batuco-Liray | From 3 to 4 lanes per direction over 10.7 km |
| Third lanes | Batuco-Liray to the El Melón tunnel's southern access | About 102 km in both directions; the Las Chilcas grade keeps its profile |
| New service roads | Lampa, Tiltil, Llay-Llay, Hijuelas, La Calera, Nogales | Plus improving and paving existing ones |
| Interchanges and bridges | Whole section | New and renewed interchanges; replacement of bridges past their service life |
| Footbridges | Whole section | Renewal of most existing ones |
| Free-flow tolling | Toll plazas | Progressive replacement of barrier tolling |
Source: Diario Financiero, project file in the SEIA and MOP concession page. Design speeds will be 120 and 100 km/h, with 80 km/h on the Las Chilcas grade, according to the MOP.

The second Route 5 Santiago-Los Vilos concession
The project is part of a larger contract. The MOP awarded the second concession of the Santiago-Los Vilos section to VíasChile through supreme decree No. 163 of November 2, 2024, with an official budget of UF 28,288,000 (see what the UF is). The concession, which includes the El Melón tunnel, began on February 20, 2025, and has a variable term of up to 30 years, according to the MOP concession page.
| Item | Second Santiago-Los Vilos concession |
|---|---|
| Concessionaire | VíasChile (Sociedad Concesionaria Nueva Aconcagua S.A.) |
| Total length | 218.2 km, from km 10.86 to km 229.1 (including the El Melón grade) |
| Official budget | UF 28.288.000 |
| Award decree | MOP Supreme Decree No. 163, November 2, 2024 |
| Concession start | February 20, 2025 |
| Term | Variable, up to 30 years |
| Municipalities | Quilicura, Colina, Lampa, Tiltil, Llay-Llay, Hijuelas, La Calera, Nogales, Zapallar, La Ligua, Papudo, Los Vilos |
| Project filed with the SEIA | Section 1: Santiago-El Melón tunnel (km 10.86 to 127.1), US$456.2 million |
Source: MOP concession page and project file in the SEIA. The MOP mentions 218 km of improvements and 223.4 km elsewhere on the same page; the EIA uses 218.2 km. The concessionaire's toll sheet cites MOP Supreme Decree No. 44080 of 2025 as the award decree, different from the one reported by the MOP.
The EIA is filed as a modification of an existing project: the highway predates the SEIA and was never environmentally rated, except for the urban access to Santiago, approved under RCA No. 419 of 2012 after a US$130 million environmental impact statement filed in 2011. The new project is three and a half times larger and, as an environmental impact study, includes a mandatory public participation process.
Free flow on Route 5 North: what changes at the tolls
Free flow already works on part of the route. Since August 7, 2026, the Las Vegas and Pichidangui plazas charge through gantries that read the TAG transponder and license plate, without stopping, according to Nueva Aconcagua. Any highway's TAG works and the toll is the same as at the booth. Drivers without a TAG must pay the trip on the concessionaire's website: from 72 business hours and within 30 calendar days a factor of 1.25 is applied to the toll; after that, the trip is reported to the MOP as a traffic law violation, according to Nueva Aconcagua 2026 tolls.
| Toll plaza | Cars and pickups | 2-axle buses and trucks | Buses and trucks with 3+ axles | Motorcycles |
|---|---|---|---|---|
| Lampa | $900 | $1,600 | $2,900 | $300 |
| Las Vegas | $2,900 | $5,300 | $9,400 | $900 |
| Pichidangui | $2,900 | $5,300 | $9,400 | $900 |
| El Melón tunnel | $2,900 | $5,300 | $9,400 | $900 |
Source: Nueva Aconcagua 2026 tolls, in force from January 1 to December 31, 2026, every day and in both directions. The side plazas (Lo Marcoleta, Buenaventura, La Montaña and Lo Pinto) have peak and off-peak rates: for cars they range from 181 to 486 pesos off-peak and from 362 to 972 pesos at peak. Las Vegas residents defined by the government inspector pay a special 100-peso rate.

When Route 5 North works would begin
According to the MOP schedule cited by Diario Financiero, works would start in March 2029, provided the environmental process takes no more than 30 months, and final commissioning would be in the first half of 2033. An EIA has a legal review period of 120 business days, extendable to 180, under article 15 of Law 19,300, but suspensions so the developer can answer observations usually lengthen the process. The project is reviewed by the SEA's Executive Directorate because it spans more than one region, and its categories include works in protected areas and urban wetlands.
- Jul 14, 2023Call for tenders
- Aug 14, 2024Economic bids opened
- Nov 2, 2024Award decree to VíasChile
- Feb 20, 2025VíasChile takes over the concession
- Aug 7, 2026Free flow at Las Vegas and Pichidangui
- Nov 23, 2026EIA filed with the SEIA
- Mar 2029Works begin (if review takes under 30 months)
- H1 2033Final commissioning
The SEIA is already reviewing other large transport projects in central Chile, such as the final section of Santiago's Metro Line 9. For Route 5 North users, the practical step is to have an active TAG and an up-to-date vehicle circulation permit.
Frequently asked questions
Which section of Route 5 North will be widened?
From kilometer 10.86, at Santiago's northern exit (Quilicura), to kilometer 127.1, at the El Melón tunnel's southern access (Nogales): more than 116 km.
How much does the project cost?
US$456.2 million, according to the environmental impact study filed with the SEIA on November 23, 2026.
Will tolls rise with free flow?
The concessionaire says free flow does not change current tolls. Drivers without a TAG pay a 25% surcharge if they settle within 30 days.
When would the new lanes be ready?
Final commissioning is planned for the first half of 2033, with works from March 2029 if the environmental review takes no more than 30 months.